Banksia Road Cell 12 & Leachate Pond no. 3 Design & Construction
WML was engaged to design the earthworks, lining system and leachate extraction system for the next waste storage cell at the Banksia Road waste facility in Dardanup, Cell 12, as well as the next leachate storage pond, pond no. 3.
Project Description

After completion of the design and tender phases, Transpacific retained WML to provide construction superintendence for the works
including daily inspections, progress claim certification for payment, variation orders, site meetings etc.
WML also compiled a Construction Completion CQA report for submission to DEC, demonstrating compliance with the VicBEPM.


WML Services
Contact Us Today
At WML Consultants, we take great pride in all of our work. From the first stages of planning and design, down to the crucial aspects of project management, our team is with you every step of the way. Our highly experienced and knowledgeable engineers are here to ensure your project is completed within your timeframe and budget.
Experience just how accessible we are. Talk to us today.