Water Corperation

Refurbishment of Bridge over Buananyup Drain on Florence Road

Bridge 43 is a four span single lane timber bridge and is located on Florence Road in the Shire of Busselton crossing the Buayanyup Drain. Project Value $400,000 amd WML Fee $55,000

Project Description

The complete upgrades by WMLs structural engineering consultants to the Buananyup bridge.

The bridge had a timber substructure and superstructure except for Abutment 1 which is stone masonry and Pier 2 which is reinforced concrete.

The elements of the bridge that required rectification work included:

  • Piles and halfcaps on Pier 1
  • Pile on Pier 3
  • All of Abutment 2
  • Replacement of Stringers in Span 1, 2, 3 and 4.
  • Corbel at Pier 2
  • Concrete overlay on deck
  • Safety barriers
  • Pile banding and stringer bolting
  • Minor maintenance of timber elements such as end grain sealing and bolt tightening.

The bridge had deteriorated to a poor condition and the load capacity of the bridge had been reduced to a 4 tonne limit. A Preliminary design study was undertaken by WML and investigated a range of options including refurbishment, construction of a new single lane bridge and construction of a new two lane bridge. The lowest NPV option was to refurbish the existing bridge to its original load capacity and this recommendation was adopted by the client.

WML undertook the detailed design of the refurbishment and undertook construction inspections to ensure that compliance with the drawings and specifications was achieved.

WML Services

Structural design

Civil engineering design

Contact Us Today

Experience just how accessible we are. Talk to us today.

WML Consultants Logo. Regional Engineering in Western Australia

WML Consultants is a consulting engineering company specialising in road engineering, civil engineering, structural engineering, geotechnical engineering, contract administration and project management.

© 2016 WML.